|
Daniel Marr & Son Co.
v. Coreslab Structures (Conn), Inc., 2005
Mass. Super. LEXIS 545 (Nov. 21, 2005) (van
Gestel, J.). |
|
The Plaintiff, Daniel Marr, was a
sub-subcontractor to the Defendant, Coreslab, in
connection with the construction of One Lincoln Street,
a thirty-six story building in Boston. Coreslab, as a
subcontractor to the general contractor, was
responsible, among other things, for the design and
engineering of the pre-cast concrete panels. Daniel
Marr’s responsibilities included unloading the panels,
attaching them to the building structure and ensuring
that the panels were properly aligned.
As is true for even the smallest
construction projects, things did not proceed as
planned. In the midst of the project, the general
contractor directed Coreslab to alter the sequence for
erecting the panels. Instead of attaching the panels one
floor at a time in a wrap-around fashion, the general
contractor instructed Coreslab (who in turn ordered
Daniel Marr) to attach the panels by elevation, so that
one side of the building was completed at a time. Daniel
Marr sued Coreslab, the general contractor (Beacon
Skanska Construction Co.) and Liberty Mutual Insurance
Company, which had posted a bond upon Daniel Marr filing
a mechanics lien. Daniel Marr settled with the GC prior
to trial and proceeded against Coreslab and Liberty.
Daniel Marr claimed that the out-of-sequence erection of
the panels required it to mobilize and |
|
demobilize its crew and to align the
panels repeatedly as sides of the building were
complete. Daniel Marr also claimed that Coreslab
breached the contract in three additional specific
respects. In total, Daniel Marr claimed damages of
approximately $1.25 million. The Court found in favor of
Daniel Marr.
Of particular interest is the Court’s
discussion of Daniel Marr’s burden of proving its
damages. Although Daniel Marr sought additional
compensation arising out of four separate issues, the
Court held that it had specifically proven its damages
only with respect to the panel sequencing issue. The
Court, however, appeared to award full recovery to
Daniel Marr. The Court noted that the changes mandated
by Coreslab “made it impossible for Marr to determine
its losses on a segregated basis.” The Court held that
“when there is an increase in work on a project, the
measure of damages to which a a contractor or
subcontractor is entitled is the fair price of the
additional work” and that Marr was “entitled to recovery
for the fair value for the work done.” The Court
credited the testimony of one of the losing bidders on
the project, who testified that the amount of work spent
by Marr was reasonable. The Court held that Marr had
satisfied its burden of proving its damages “with a
reasonable degree of certainty.”
 |