A quarterly summary and brief analysis of significant decisions issued by the Massachusetts Superior Court Business Litigation Session. A service of O’Connor, Carnathan and Mack LLC.
 

July
2008

Volume 4
Number 4
Page 7

 

Summarizing opinions from Oct 1, 2007 through
Dec. 31, 2007

 

 


 
 

 

 

 

 

 

 


 

 



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 



 

 

     

O  T  H  E  R      D  E  C  I  S  I  O  N  S  :

Nates v. Larkin, 2007 WL 4442361 (Mass. Super.)
(Dec. 5, 2007) (Fabricant, J.).

     

This action alleged building defects and breaches of fiduciary duties in connection with the construction of Millennium Place, a large-scale condominium project in downtown Boston. The primary condominium board included representatives from each residential association; however, it was controlled by representatives of the commercial association who were appointed by the project’s developer. When members of the residential associations identified defects in the buildings and demanded that the primary association take action against the developer to have these defects corrected, the primary association refused. The president of a residential association brought suit against the developer-appointed board members, the developer itself, the construction manager, and a number of the project’s architects and engineers. Several Defendants moved to dismiss.

The Court first considered the motion to dismiss brought by the developer and its representatives on the board. This motion asserted that Plaintiff lacked standing to sue, on the grounds that the residential association rather than its president was the real party in interest. The Court agreed that it was the residential association – not its president – that had the statutory authority to sue and the standing to bring a derivative claim on behalf of the primary association. But it did not follow that dismissal was therefore in order; rather, the proper course under Mass. R. Civ. P. Rule 17(a) was to grant the Plaintiff a reasonable amount of time to amend the complaint and substitute the real party in interest as Plaintiff. Id. at *4.

The Court then considered the motion brought by the construction manager and joined by the architect of record. This motion first asserted that Plaintiff failed to state a claim for breach of contract insofar the complaint did not allege a contractual relationship between the residential association and the construction manager. Plaintiff attempted to salvage this claim under a third-party beneficiary theory, which requires a Plaintiff to “show that the parties to the contract intended to give the Plaintiff the benefit of the promised performance.” Id. at *5. But in this case, “the express language of the contract establishes the absence of any such intent …. The contract claim therefore must be dismissed for failure to state a claim.” Id.

The construction manager’s motion also sought dismissal of Plaintiff’s negligence claim under the economic lossdoctrine, which “bars recovery in the

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 



 

 

 

 

 

 

 



 

 

absence of personal injury or physical damage to property other than the property alleged to have been negligently constructed.” Id. Nothing in Plaintiff’s complaint or supporting materials suggested personal injury. As for damage to property, Plaintiff’s materials were ambiguous at best. But at the motion to dismiss stage, the Court was required to “read the complaint and its attachments broadly, drawing all reasonable inferences in favor of the Plaintiffs.” Id. Under that standard, the Court could not conclude “that the complaint fails to allege any set of facts on which relief could be granted.” Id.

Turning to the timeliness of Plaintiff’s negligence claims, the Court observed that G.L. c. 260, § 2B provides both a statute of repose and a statute of limitations applicable to claims of negligence in connection with building construction. “The issuance of a certificate of occupancy officially opens a building to use, and therefore triggers the start of the six year period under the statue of repose.” Id. at *6. In this case, certificates were issued more than six years prior to the commencement of suit; however, these certificates were only temporary and only for certain parts of the buildings. The Court found no Massachusetts case addressing the effect of temporary certificates on the statute of repose, but followed the federal district Court in holding that such certificates do commence the repose period in the absence of any limitations expressed therein respecting the use to be made of the building. Id. Nevertheless, the evidence before the Court did not clearly establish whether the certificates issued for the project covered the portions of the building at issue. Id. at *7. The three-year statute of limitations likewise did not bar the claims, since it was unclear from the record when Plaintiff reasonably should have discovered the alleged defects. Id.

The construction manager’s motion also asserted that Plaintiff failed to meet the requirements for a derivative action under Mass. R. Civ. P. Rule 23.1. The Court held that “although the point could have been made more expressly, the complaint does adequately allege that it is brought on behalf of the primary association.” Id. at *8. The Court further held that a demand on the members of the primary association would have been futile, given the fact that it was controlled by the developer. The Court also held that Plaintiff adequately represented the interests of the primary association, notwithstanding the fact that some members of the association did not consent to Plaintiff’s suit. Id. at *9.


 
 

 

 

 

 

 


 

 






 

 

 

 

 

 

 


 

 

 

 

 

 

 

 



 

 
P A G E
1  2  3  4  5  6  7  8  9  10